Project projections show that the project will fall behind in the testing phrase. This event was documented as a known risk at the project’s beginning due to the time to market imperative because the project is currently in the analysis phrase, the project manager decides to outsource the testing function and begin discussions with the chosen vendor.Of which risk strategy is this an example?
A、Avoidance
B、Transference
C、Sharing
D、Mitigation