Your boss , the vice president of research at your electronic system development firm , defines success on the project as providing “state-of-the-art” development . The vice president of marketing defines it as “world-class primarily .” The vice president of engineering , who is the customer for this project , is primarily concerned with new features .Which of the following BEST describes what should you do?
A、Make sure the requirements are defined in measurable terms.
B、Concentrate on new features
C、Identify additional stakeholders that want new features to shift the balance in that direction
D、Concentrate on making the project state-of-the-art