成人学院中文字幕,国产午夜麻豆影院在线观看,久久男人免费视频,久久精品美女视频,www.福利视频,蜜桃一本色道久久综合亚洲精品冫,欧美三级视频

軟題庫 移動APP 掃碼下載APP 隨時隨地移動學(xué)習(xí) 培訓(xùn)課程
試卷名稱 信息系統(tǒng)項目管理師-pmp練習(xí)題-2
考試中心《信息系統(tǒng)項目管理師-pmp練習(xí)題-2》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

A project is using a productive infrastructure in a large operating environment. The project is an accident occurred at this time, but a technical solution is implemented to resolve the problem. Despite the circumstances a project stakeholders are still complaints because:
A、The project sponsor had not received any notification, and without the approval of the chosen option.
B、 The risk was not identified and assessed, and update in the risk log.
C、 The change control board was informed, and the incident was not evaluated.
D、 The change created a risk that could have caused a major operational impact.


相關(guān)試題

推薦文章
合作網(wǎng)站內(nèi)容