成人学院中文字幕,国产午夜麻豆影院在线观看,久久男人免费视频,久久精品美女视频,www.福利视频,蜜桃一本色道久久综合亚洲精品冫,欧美三级视频

軟題庫(kù) 移動(dòng)APP 掃碼下載APP 隨時(shí)隨地移動(dòng)學(xué)習(xí) 培訓(xùn)課程
試卷名稱(chēng) 信息系統(tǒng)項(xiàng)目管理師-pmp練習(xí)題-1
考試中心《信息系統(tǒng)項(xiàng)目管理師-pmp練習(xí)題-1》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

Four months into a 10-month project, the project manager realizes that the project is behind schedule and slippage will lead to an overrun of 25% of the project’s budget. A change request is created, but when the project manager seeks approval, the executive is reluctant to do so. What could be the reason for this executive’s reluctance ?
A、Lack of the project management plan approval.
B、 Lack of the risk management plan approval.
C、 Lack of the communications management plan approval.
D、 Lack of the change management plan approval.


相關(guān)試題

推薦文章